- SR 520 Montlake
- Delta Sky Way LAX Terminal 2 & 3 Modernization
- Sound Transit O&M Facility East
- I-64 Corridor Hampton Road Bridge Tunnel Expansion
- San Francisco International Airport Sustainability and Energy Services
- SeaTac North Satellite Expansion
- Alaskan Way Viaduct / SR 99 Tunnel Replacement
- LA County Metropolitan Transportation Authority Expo Line Operations & Maintenance Facility
- McCarran Airport - Central Utility Plant
- San Francisco International Airport
- SeaTac Airport Rental Car Facility
- Vacaville Transportation Center
- LA Metro Southwestern Yard Crenshaw/LAX Transit Corridor
- Caltrans District 3 Headquarters
McCarran Airport – Central Utility Plant
Las Vegas, Nevada, United States
The Terminal 3 Central Utility Plant is a new structure with an exterior utility yard. The facility is designed with sufficient capacity to serve Terminal 3, Concourse D, and the Automated Transit System (ATS) and stations that link these two facilities.
The plant has 11,000 tons of cooling capacity from five 2,200-ton, variable primary flow centrifugal chillers; an additional 2,200-ton centrifugal chiller is provided as stand-by. The chillers are served by five field erected concrete cooling towers; these also utilize an additional cell that is provided as standby.
The hot water system consists of six (6) 21,000 MBH heating hot water boilers with flexible water tubes, and an additional 21,000 MBH unit as standby. There are four 2,500 KVA diesel generators that provide emergency power to both Terminal 3 and the Central Utility Plant.
Glumac commissioning agents were involved early in project development, providing a peer review of the design documents and specifications and submittal reviews. Since the central plant is part of a much larger master plan of the airport, Glumac assisted in the coordination between the numerous contractors to verify the equipment and systems are installed correctly the first time. Glumac also provided commissioning services for the plant.
Size: 48,000 sf
Project cost: $67.7 Million
End Date: January 2010
Contractor: Penta Building Group
Owner: McCarran International Airport
Services: Commissioning